SOWPARNIKA RIVER VIEW GARDENS PHASE 5
CompletedStatus is from the dates they filed. Not a court finding.
Building
SOWPARNIKA RIVER VIEW GARDENS PHASE 5
Who is building it
Sowparnika Projects
Official number
K-RERA/PRJ/147/2021 · 23 Jul 2021
Where
NEMOM, Thiruvananthapuram, 695019
Type
Apartments
Promised ready date
31 Dec 2024
they did not change this date on file
How much they say is done
100%
this is what they filed on 07 Jul 2023
How many already sold
50 of 50
100% flats sold
Complaints
5
4 already decided
Last update to K-RERA
not needed
project is closed on the register
On the register
Units
50
Booked count
50
Escrow bank
Axis Bank Ltd
Legal case
Yes
Complaints before K-RERA · 5
93/2022 · Authority
final order
90/2020 · Authority
final order
61/2022 · Authority
final order
12/2022 · Adjudicating Officer
final order
126/2020 · Authority
pending