Skip to main content
Enthayi?
K-RERA
← Projects

Compare

Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Kollam · 2021 · K-RERA/PRJ/064/2021

Kollam · 2021 · K-RERA/PRJ/KLM/078/2021

Same cohort: Kollam · 2021.

As filed
Project
KSK MOUNT CASTLE
MELILA, Kollam
KCHELL RESIDENCY
SHAKTHIKULANGARA, Kollam
Promised date
31 Dec 2022
no date change on file
06 Jun 2019
no date change on file
Physical %
100%
filed 10 Jan 2023
100%
not filed
Booked %
0%
0 of 6
44%
30 of 68
Complaints
none on file
from the public complaints list
2
2 final orders
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.