Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Ernakulam · 2021 · K-RERA/PRJ/129/2021
Ernakulam · 2021 · K-RERA/PRJ/114/2021
Same cohort: Ernakulam · 2021.
Project
JKH SIGNATURE
KEEZHMAD, Ernakulam
DREAMFLOWER LA-CASITA
VAZHAKKALA, Ernakulam
Promised date
30 Dec 2022
45 months past promised date
31 Jan 2024
no date change on file
Physical %
45%
filed 19 Dec 2022
100%
filed 14 Jan 2023
Booked %
42%
21 of 50
100%
40 of 40
Complaints
11
5 final orders
none on file
from the public complaints list
Last QPR
Q1 2025
filed 07 Jul 2025 · 423d ago · Stale
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.