Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Thiruvananthapuram · 2021 · K-RERA/PRJ/144/2021
Thiruvananthapuram · 2021 · K-RERA/PRJ/090/2021
Same cohort: Thiruvananthapuram · 2021.
Project
GIE ROYAL ORCHID
KOWDIAR, Thiruvananthapuram
Oceanus Sunshine Phase I
ATTIPRA, Thiruvananthapuram
Promised date
30 Jun 2022
51 months past promised date
29 Oct 2020
moved +1 mo from 29 Sept 2020
Physical %
98%
filed 08 Feb 2023
0%
filed 04 Jul 2023
Booked %
72%
36 of 50
100%
68 of 68
Complaints
4
3 final orders
none on file
from the public complaints list
Last QPR
Q2 2026
filed 05 Oct 2026 · -32d ago · Current
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.