Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Kozhikode · 2021 · K-RERA/PRJ/046/2021
Kozhikode · 2021 · K-RERA/PRJ/106/2021
Same cohort: Kozhikode · 2021.
Project
BAMBOO PARK II
PERUVAYAL, Kozhikode
LANDMARK WORLD ENTASIS, LANDMARK WORLD FRIEZE
OLAVANNA, Kozhikode
Promised date
31 Dec 2023
no date change on file
30 Dec 2021
no date change on file
Physical %
100%
not filed
100%
filed 31 Oct 2022
Booked %
0%
0 of 49
73%
121 of 166
Complaints
none on file
from the public complaints list
1
1 final order
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.