Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2021 · K-RERA/PRJ/012/2021

Ernakulam · 2021 · K-RERA/PRJ/080/2021

Same cohort: Ernakulam · 2021.

As filed
Project
MYS FORTUNE APARTMENTS
VAZHAKKALA, Ernakulam
BREEZY MEADOWS
NADAMA, Ernakulam
Promised date
29 Feb 2024
moved +6 mo from 30 Aug 2023
30 Dec 2024
20 months past promised date
Physical %
100%
filed 20 Oct 2023
50%
filed 07 Nov 2023
Booked %
—
unit count not filed
94%
15 of 16
Complaints
none on file
from the public complaints list
2
no final order on file
Last QPR
N/A
closed on the register — QPR not expected
Q1 2026
filed 10 Jul 2026 · 55d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.