Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2022 · K-RERA/PRJ/ERN/021/2022

Ernakulam · 2022 · K-RERA/PRJ/ERN/086/2022

Same cohort: Ernakulam · 2022.

As filed
INFRA PROXIMCompleted
Project
INFRA PROXIM
EDAPPALLY NORTH, Ernakulam
Padmasree Ramsarovar
NADAMA, Ernakulam
Promised date
01 Jul 2022
no date change on file
01 Jun 2025
15 months past promised date
Physical %
100%
not filed
75%
filed 26 Aug 2023
Booked %
100%
31 of 31
50%
10 of 20
Complaints
5
1 final order
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
Q1 2025
filed 07 Jul 2025 · 423d ago · Stale

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.