Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Kottayam · 2021 · K-RERA/PRJ/101/2021
Kottayam · 2021 · K-RERA/PRJ/163/2021
Same cohort: Kottayam · 2021.
Project
JEWEL WATERLILLY
MUTTAMBALAM, Kottayam
CJs HARITHA CITY PLAZA
MUTTAMBALAM, Kottayam
Promised date
15 May 2014
no date change on file
30 Oct 2021
moved +6 mo from 30 Apr 2021
Physical %
100%
filed 22 Jul 2023
100%
not filed
Booked %
73%
41 of 56
16%
12 of 75
Complaints
2
2 final orders
2
1 final order
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.