Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2020 · K-RERA/PRJ/130/2020

Ernakulam · 2020 · K-RERA/PRJ/235/2020

Same cohort: Ernakulam · 2020.

Project
Confident White Berry
KAKKANAD, Ernakulam
Sobha Atlantis Phase 1 block 3 and 4
NADAMA, Ernakulam
Promised date
01 Nov 2025
10 months past promised date
30 Oct 2026
no date change on file
Physical %
88%
filed 07 Oct 2023
98%
filed 07 Oct 2023
Booked %
89%
85 of 95
80%
154 of 192
Complaints
none on file
from the public complaints list
none on file
legal case marked on register
Last QPR
Q2 2025
filed 06 Oct 2025 · 332d ago · Stale
Q2 2026
filed 07 Oct 2026 · -34d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.