Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Palakkad · 2020 · K-RERA/PRJ/303/2020
Palakkad · 2020 · K-RERA/PRJ/078/2020
Same cohort: Palakkad · 2020.
Project
VATIKA VILLAS
OTTAPALAM I, Palakkad
Jayaraj Divya
PALAKKAD-2, Palakkad
Promised date
07 Dec 2022
46 months past promised date
30 Jun 2023
moved +6 mo from 31 Dec 2022
Physical %
71%
not filed
100%
not filed
Booked %
63%
5 of 8
100%
16 of 16
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q3 2024
filed 07 Jan 2025 · 604d ago · Stale
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.