Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Kannur · 2021 · K-RERA/PRJ/KNR/010/2021

Kannur · 2021 · K-RERA/PRJ/198/2021

Same cohort: Kannur · 2021.

As filed
ASSET CHAMBERCompleted
Sailors CoveOn Track
Project
ASSET CHAMBER
ELAYAVOOR, Kannur
Sailors Cove
CHIRAKKAL, Kannur
Promised date
30 Jun 2025
no date change on file
30 Oct 2026
no date change on file
Physical %
100%
filed 06 Oct 2023
—
not filed
Booked %
100%
82 of 82
30%
64 of 211
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
never filed
no quarterly update on file

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.