Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Ernakulam · 2020 · K-RERA/PRJ/272/2020
Ernakulam · 2020 · K-RERA/PRJ/325/2020
Same cohort: Ernakulam · 2020.
Project
GALAXY BRIDGEWOOD
ELAMKULAM, Ernakulam
OLIVE OURANIA
EDAPPALLY NORTH, Ernakulam
Promised date
30 Sept 2022
48 months past promised date
30 Sept 2024
moved +6 mo from 31 Mar 2024
Physical %
95%
not filed
100%
not filed
Booked %
92%
101 of 110
72%
36 of 50
Complaints
10
3 final orders
none on file
from the public complaints list
Last QPR
Q1 2025
filed 02 Jul 2025 · 428d ago · Stale
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.