Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Ernakulam · 2020 · K-RERA/PRJ/272/2020
Project
GALAXY BRIDGEWOOD
ELAMKULAM, Ernakulam
—
pick a project
Promised date
30 Sept 2022
48 months past promised date
—
Physical %
95%
not filed
—
Booked %
92%
101 of 110
—
Complaints
10
3 final orders
—
Last QPR
Q1 2025
filed 02 Jul 2025 · 428d ago · Stale
—
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.