Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2020 · K-RERA/PRJ/263/2020

Ernakulam · 2020 · K-RERA/PRJ/235/2020

Same cohort: Ernakulam · 2020.

Project
GALAXY EMERALD
ELAMKULAM, Ernakulam
Sobha Atlantis Phase 1 block 3 and 4
NADAMA, Ernakulam
Promised date
19 Nov 2022
46 months past promised date
30 Oct 2026
no date change on file
Physical %
85%
not filed
98%
filed 07 Oct 2023
Booked %
88%
65 of 74
80%
154 of 192
Complaints
9
6 final orders
none on file
legal case marked on register
Last QPR
Q1 2025
filed 02 Jul 2025 · 428d ago · Stale
Q2 2026
filed 07 Oct 2026 · -34d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.