Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Ernakulam · 2020 · K-RERA/PRJ/263/2020
Project
GALAXY EMERALD
ELAMKULAM, Ernakulam
—
pick a project
Promised date
19 Nov 2022
46 months past promised date
—
Physical %
85%
not filed
—
Booked %
88%
65 of 74
—
Complaints
9
6 final orders
—
Last QPR
Q1 2025
filed 02 Jul 2025 · 428d ago · Stale
—
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.