Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Ernakulam · 2021 · K-RERA/PRJ/104/2021
Project
JEWEL CAPITAL
EDAPPALLY SOUTH, Ernakulam
—
pick a project
Promised date
31 Dec 2025
8 months past promised date
—
Physical %
82%
filed 27 Dec 2023
—
Booked %
10%
9 of 88
—
Complaints
none on file
from the public complaints list
—
Last QPR
Q4 2025
filed 14 Jul 2026 · 51d ago · Current
—
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.