Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Palakkad · 2020 · K-RERA/PRJ/318/2020

Palakkad · 2020 · K-RERA/PRJ/282/2020

Same cohort: Palakkad · 2020.

As filed
OMG MAGNUSCompleted
Project
HANCO SIVAM
PALAKKAD I, Palakkad
OMG MAGNUS
VANIYAKULAM II, Palakkad
Promised date
31 Mar 2024
30 months past promised date
10 Aug 2023
no date change on file
Physical %
69%
not filed
100%
not filed
Booked %
0%
0 of 29
80%
8 of 10
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q2 2026
filed 12 Oct 2026 · -39d ago · Current
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.