Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Thrissur · 2020 · K-RERA/PRJ/324/2020

Thrissur · 2020 · K-RERA/PRJ/271/2020

Same cohort: Thrissur · 2020.

Project
ELITE LA PRISTINE PHASE 1
ADAT, Thrissur
CHURCH GATE 1
AVANISSERY, Thrissur
Promised date
31 Dec 2023
no date change on file
31 Jul 2024
25 months past promised date
Physical %
100%
not filed
0%
not filed
Booked %
77%
36 of 47
82%
9 of 11
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
Q1 2025
filed 25 Jun 2025 · 435d ago · Stale

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.