Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Thrissur · 2021 · K-RERA/PRJ/112/2021
Thrissur · 2021 · K-RERA/PRJ/TSR/001/2021
Same cohort: Thrissur · 2021.
Project
CIDBI CANDOR
THRISSUR, Thrissur
PB ROYAL NEST
PUZHAKKAL, Thrissur
Promised date
20 Dec 2025
no date change on file
30 Jun 2023
no date change on file
Physical %
100%
not filed
100%
filed 07 Jan 2023
Booked %
100%
44 of 44
100%
8 of 8
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.