Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Ernakulam · 2020 · K-RERA/PRJ/011/2020
Ernakulam · 2020 · K-RERA/PRJ/274/2020
Same cohort: Ernakulam · 2020.
Project
ASSET MOON GRACE
ERNAKULAM, Ernakulam
Classic Avenir Suites
THRIKKAKARA NORTH, Ernakulam
Promised date
30 May 2025
no date change on file
30 Jun 2022
no date change on file
Physical %
100%
filed 06 Oct 2023
100%
filed 31 Oct 2022
Booked %
57%
27 of 47
100%
34 of 34
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.