Skip to main content
Enthayi?
K-RERA
← Projects

Compare

Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Thiruvananthapuram · 2020 · K-RERA/PRJ/256/2020

Thiruvananthapuram · 2020 · K-RERA/PRJ/085/2020

Same cohort: Thiruvananthapuram · 2020.

As filed
SFS WEST HILLCompleted
ANTHEMCompleted
Project
SFS WEST HILL
KARAKULAM, Thiruvananthapuram
ANTHEM
KOWDIAR, Thiruvananthapuram
Promised date
31 Mar 2024
no date change on file
31 Dec 2024
no date change on file
Physical %
100%
filed 07 Oct 2023
100%
filed 07 Oct 2023
Booked %
97%
107 of 110
100%
56 of 56
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.