Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Kozhikode · 2020 · K-RERA/PRJ/119/2020

Kozhikode · 2020 · K-RERA/PRJ/037/2020

Same cohort: Kozhikode · 2020.

As filed
Project
50 CROSS ROADS
KASABA, Kozhikode
TRITON CRESCENT
NELLIKODE, Kozhikode
Promised date
30 Sept 2021
no date change on file
31 May 2023
no date change on file
Physical %
100%
not filed
100%
filed 06 Jul 2023
Booked %
54%
25 of 46
100%
97 of 97
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.