Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2021 · K-RERA/PRJ/041/2021

Ernakulam · 2021 · K-RERA/PRJ/054/2021

Same cohort: Ernakulam · 2021.

As filed
RDS LEGACYCompleted
Project
Riddhi Siddhi Apartment
MATTANCHERRY, Ernakulam
RDS LEGACY
ELAMKULAM, Ernakulam
Promised date
30 Jun 2023
no date change on file
05 Dec 2019
no date change on file
Physical %
100%
filed 07 Jan 2023
100%
not filed
Booked %
13%
2 of 15
100%
48 of 48
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.