Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Ernakulam · 2020 · K-RERA/PRJ/253/2020
Ernakulam · 2020 · K-RERA/PRJ/007/2020
Same cohort: Ernakulam · 2020.
Project
Marina One Phase 3
ERNAKULAM, Ernakulam
DREAMFLOWER MAGNUM OPUS
EDAPPALLY SOUTH, Ernakulam
Promised date
30 Oct 2027
no date change on file
31 Dec 2022
no date change on file
Physical %
87%
filed 07 Oct 2023
100%
filed 16 Feb 2023
Booked %
98%
177 of 181
100%
42 of 42
Complaints
none on file
legal case marked on register
none on file
from the public complaints list
Last QPR
Q2 2026
filed 07 Oct 2026 · -34d ago · Current
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.