Skip to main content
Enthayi?
K-RERA
← Projects

Compare

Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Thrissur · 2021 · K-RERA/PRJ/TSR/001/2021

Thrissur · 2021 · K-RERA/PRJ/TSR/020/2021

Same cohort: Thrissur · 2021.

As filed
PB ROYAL NESTCompleted
FORUS GAZANIACompleted
Project
PB ROYAL NEST
PUZHAKKAL, Thrissur
FORUS GAZANIA
THRISSUR, Thrissur
Promised date
30 Jun 2023
no date change on file
31 Dec 2027
no date change on file
Physical %
100%
filed 07 Jan 2023
100%
filed 05 Oct 2023
Booked %
100%
8 of 8
91%
40 of 44
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.