Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Thiruvananthapuram · 2021 · K-RERA/PRJ/TVM/017/2021
Thiruvananthapuram · 2021 · K-RERA/PRJ/090/2021
Same cohort: Thiruvananthapuram · 2021.
Project
Dasco Royal Valley Phase 2
VEMBAYAM, Thiruvananthapuram
Oceanus Sunshine Phase I
ATTIPRA, Thiruvananthapuram
Promised date
05 May 2024
no date change on file
29 Oct 2020
moved +1 mo from 29 Sept 2020
Physical %
100%
filed 31 Jul 2023
0%
filed 04 Jul 2023
Booked %
55%
6 of 11
100%
68 of 68
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.