Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Ernakulam · 2020 · K-RERA/PRJ/043/2020
Ernakulam · 2020 · K-RERA/PRJ/235/2020
Same cohort: Ernakulam · 2020.
Project
ANTA - KINGS PLACE
NADAMA, Ernakulam
Sobha Atlantis Phase 1 block 3 and 4
NADAMA, Ernakulam
Promised date
30 May 2023
40 months past promised date
30 Oct 2026
no date change on file
Physical %
42%
not filed
98%
filed 07 Oct 2023
Booked %
12%
8 of 67
80%
154 of 192
Complaints
20
1 final order
none on file
legal case marked on register
Last QPR
Q3 2024
filed 06 Feb 2025 · 574d ago · Stale
Q2 2026
filed 07 Oct 2026 · -34d ago · Current
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.