Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Ernakulam · 2020 · K-RERA/PRJ/043/2020
Ernakulam · 2020 · K-RERA/PRJ/325/2020
Same cohort: Ernakulam · 2020.
Project
ANTA - KINGS PLACE
NADAMA, Ernakulam
OLIVE OURANIA
EDAPPALLY NORTH, Ernakulam
Promised date
30 May 2023
40 months past promised date
30 Sept 2024
moved +6 mo from 31 Mar 2024
Physical %
42%
not filed
100%
not filed
Booked %
12%
8 of 67
72%
36 of 50
Complaints
20
1 final order
none on file
from the public complaints list
Last QPR
Q3 2024
filed 06 Feb 2025 · 574d ago · Stale
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.