Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Kozhikode · 2026 · K-RERA/PRJ/KKD/138/2026

Kozhikode · 2026 · K-RERA/PRJ/KKD/038/2026

Same cohort: Kozhikode · 2026.

Project
HiLITE LEPTIS
OLAVANNA, Kozhikode
REIGATE MONTE MIRAGE -PHASE 2
PUTHIYANGADI, Kozhikode
Promised date
06 Jan 2021
no date change on file
30 Sept 2029
no date change on file
Physical %
—
not filed
12%
not filed
Booked %
100%
75 of 75
44%
8 of 18
Complaints
1
1 final order
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
Q2 2026
filed 05 Oct 2026 · -32d ago · Current