Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Thrissur · 2026 · K-RERA/PRJ/TSR/078/2026

Thrissur · 2026 · K-RERA/PRJ/TSR/010/2026

Same cohort: Thrissur · 2026.

Project
AUREX BROOKSIDE
THRISSUR, Thrissur
CONFIDENT GRAND HEIGHTS
OLLUR, Thrissur
Promised date
30 Mar 2030
no date change on file
20 May 2031
no date change on file
Physical %
10%
not filed
1%
not filed
Booked %
9%
6 of 68
4%
3 of 81
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q2 2026
filed 07 Oct 2026 · -34d ago · Current
Q2 2026
filed 07 Oct 2026 · -34d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.