← Projects
Compare
Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Kannur · 2026 · K-RERA/PRJ/KNR/034/2026
Kannur · 2026 · K-RERA/PRJ/KNR/113/2026
Same cohort: Kannur · 2026.
Project
SREEROSH ICON
Kannur 1, Kannur
ASSET STYLUZ
Kannur 1, Kannur
Promised date
30 Apr 2031
no date change on file
14 Oct 2032
no date change on file
Physical %
26%
not filed
3%
not filed
Booked %
26%
41 of 155
4%
2 of 49
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q2 2026
filed 06 Oct 2026 · -33d ago · Current
Q2 2026
filed 07 Oct 2026 · -34d ago · Current
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.