Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Kannur · 2026 · K-RERA/PRJ/KNR/034/2026

Kannur · 2026 · K-RERA/PRJ/KNR/113/2026

Same cohort: Kannur · 2026.

As filed
ASSET STYLUZOn Track
Project
SREEROSH ICON
Kannur 1, Kannur
ASSET STYLUZ
Kannur 1, Kannur
Promised date
30 Apr 2031
no date change on file
14 Oct 2032
no date change on file
Physical %
26%
not filed
3%
not filed
Booked %
26%
41 of 155
4%
2 of 49
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q2 2026
filed 06 Oct 2026 · -33d ago · Current
Q2 2026
filed 07 Oct 2026 · -34d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.