Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Kottayam · 2026 · K-RERA/PRJ/KTM/107/2026
Kottayam · 2026 · K-RERA/PRJ/KTM/014/2026
Same cohort: Kottayam · 2026.
Project
NEPTUNE
VIJAYAPURAM, Kottayam
Eden Gardens
ONAMTHURUTH, Kottayam
Promised date
06 Sept 2027
no date change on file
30 Mar 2031
no date change on file
Physical %
—
not filed
28%
not filed
Booked %
0%
0 of 5
39%
19 of 49
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
never filed
no quarterly update on file
Q2 2026
filed 10 Oct 2026 · -37d ago · Current
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.