Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Kannur · 2026 · K-RERA/PRJ/KNR/113/2026

Kannur · 2026 · K-RERA/PRJ/KNR/112/2026

Same cohort: Kannur · 2026.

As filed
ASSET STYLUZOn Track
Project
ASSET STYLUZ
Kannur 1, Kannur
DEFENCE ENCLAVE
PERINGOM, Kannur
Promised date
14 Oct 2032
no date change on file
31 Dec 2030
no date change on file
Physical %
3%
not filed
60%
not filed
Booked %
4%
2 of 49
2%
1 of 58
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q2 2026
filed 07 Oct 2026 · -34d ago · Current
Q2 2026
filed 07 Oct 2026 · -34d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.