Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Kannur · 2025 · K-RERA/PRJ/KNR/143/2025
Kannur · 2025 · K-RERA/PRJ/KNR/042/2025
Same cohort: Kannur · 2025.
Project
Capkon Crest
Kannur 1, Kannur
SREEROSH BLUE BAY
AZHIKODE SOUTH, Kannur
Promised date
30 Oct 2030
no date change on file
30 Oct 2028
no date change on file
Physical %
11%
not filed
51%
not filed
Booked %
67%
35 of 52
33%
17 of 51
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q2 2026
filed 07 Oct 2026 · -34d ago · Current
Q2 2026
filed 06 Oct 2026 · -33d ago · Current
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.