Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Malappuram · 2025 · K-RERA/PRJ/MPM/133/2025

Malappuram · 2025 · K-RERA/PRJ/MPM/002/2025

Same cohort: Malappuram · 2025.

Project
BECORA SKY CITY - Phase 1
EZHAVATHURUHY, Malappuram
ELKOR PLATINA
PATHAIKKARA, Malappuram
Promised date
28 Nov 2030
no date change on file
29 Feb 2028
no date change on file
Physical %
25%
not filed
22%
not filed
Booked %
48%
27 of 56
84%
49 of 58
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q2 2026
filed 05 Oct 2026 · -32d ago · Current
Q2 2026
filed 03 Oct 2026 · -30d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.