Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Kozhikode · 2025 · K-RERA/PRJ/KKD/153/2025

Kozhikode · 2025 · K-RERA/PRJ/KKD/019/2025

Same cohort: Kozhikode · 2025.

As filed
Project
Brook By Residency
THAZHEKODE, Kozhikode
HiLITE OLYMPUS II
OLAVANNA, Kozhikode
Promised date
30 Jun 2026
no date change on file
30 Oct 2029
no date change on file
Physical %
100%
not filed
32%
not filed
Booked %
21%
3 of 14
94%
387 of 412
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
Q2 2026
filed 07 Oct 2026 · -34d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.