Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Palakkad · 2025 · K-RERA/PRJ/PKD/085/2025

Palakkad · 2025 · K-RERA/PRJ/PKD/032/2025

Same cohort: Palakkad · 2025.

Project
Varahanadu
KOTTATHARA, Palakkad
KMA PROPERTIES EMPYREAN AVENUE
OTTAPALAM I, Palakkad
Promised date
31 Aug 2025
12 months past promised date
12 Dec 2029
no date change on file
Physical %
—
not filed
2%
not filed
Booked %
0%
0 of 155
0%
0 of 12
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
never filed
no quarterly update on file
Q2 2026
filed 05 Oct 2026 · -32d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.