Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Thrissur · 2025 · K-RERA/PRJ/TSR/046/2025

Thrissur · 2025 · K-RERA/PRJ/TSR/010/2025

Same cohort: Thrissur · 2025.

As filed
DHARMIC WAVESCompleted
Project
DHARMIC WAVES
ARANATTUKARA, Thrissur
SANKAR ENCLAVE
PURANATTUKARA, Thrissur
Promised date
31 Jan 2030
no date change on file
03 Aug 2028
no date change on file
Physical %
100%
not filed
—
not filed
Booked %
54%
7 of 13
14%
3 of 21
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
never filed
no quarterly update on file

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.