Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Palakkad · 2025 · K-RERA/PRJ/PKD/071/2025
Palakkad · 2025 · K-RERA/PRJ/PKD/085/2025
Same cohort: Palakkad · 2025.
Project
ELEVATE
MARUTHUROAD, Palakkad
Varahanadu
KOTTATHARA, Palakkad
Promised date
13 Aug 2030
no date change on file
31 Aug 2025
12 months past promised date
Physical %
9%
not filed
—
not filed
Booked %
63%
5 of 8
0%
0 of 155
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q2 2026
filed 05 Oct 2026 · -32d ago · Current
never filed
no quarterly update on file
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.