Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2025 · K-RERA/PRJ/ERN/009/2025

Ernakulam · 2025 · K-RERA/PRJ/ERN/134/2025

Same cohort: Ernakulam · 2025.

As filed
SOPHIA NESTOn Track
Project
SOPHIA NEST
EDAPPALLY SOUTH, Ernakulam
Fern Silver Springs
KEEZHMAD, Ernakulam
Promised date
31 Dec 2027
no date change on file
08 Apr 2021
no date change on file
Physical %
—
not filed
—
not filed
Booked %
0%
0 of 4
44%
36 of 81
Complaints
none on file
from the public complaints list
flag on register
from the public complaints list
Last QPR
never filed
no quarterly update on file
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.