Skip to main content
Enthayi?
K-RERA
← Projects

Compare

Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Thrissur · 2024 · K-RERA/PRJ/TSR/260/2024

Thrissur · 2024 · K-RERA/PRJ/TSR/124/2024

Same cohort: Thrissur · 2024.

As filed
Project
Ambadi Apartments
GURUVAYUR, Thrissur
WESTFORT INEOS
IRINGAPRAM, Thrissur
Promised date
25 Mar 2027
no date change on file
20 Jun 2029
no date change on file
Physical %
65%
not filed
15%
not filed
Booked %
90%
9 of 10
21%
21 of 99
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q2 2026
filed 03 Oct 2026 · -30d ago · Current
Q2 2026
filed 06 Oct 2026 · -33d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.