Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Kottayam · 2026 · K-RERA/PRJ/KTM/055/2026
Kottayam · 2026 · K-RERA/PRJ/KTM/107/2026
Same cohort: Kottayam · 2026.
Project
OASIS MEDAOWS
MADAPPALLY, Kottayam
NEPTUNE
VIJAYAPURAM, Kottayam
Promised date
09 Feb 2030
no date change on file
06 Sept 2027
no date change on file
Physical %
—
not filed
—
not filed
Booked %
0%
0 of 21
0%
0 of 5
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
never filed
no quarterly update on file
never filed
no quarterly update on file