Skip to main content
Enthayi?
K-RERA
← Projects

Compare

Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Thrissur · 2024 · K-RERA/PRJ/TSR/261/2024

Thrissur · 2024 · K-RERA/PRJ/TSR/124/2024

Same cohort: Thrissur · 2024.

As filed
SILVER HILLSOn Track
Project
SILVER HILLS
KOLAZHY, Thrissur
WESTFORT INEOS
IRINGAPRAM, Thrissur
Promised date
21 Jun 2027
no date change on file
20 Jun 2029
no date change on file
Physical %
—
not filed
15%
not filed
Booked %
95%
73 of 77
21%
21 of 99
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
never filed
no quarterly update on file
Q2 2026
filed 06 Oct 2026 · -33d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.