Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Palakkad · 2024 · K-RERA/PRJ/PKD/127/2024

Palakkad · 2024 · K-RERA/PRJ/PKD/025/2024

Same cohort: Palakkad · 2024.

Project
BUILTECH AURA
PALAKKAD-2, Palakkad
Hanco Krishna Leela Residency
PALAKKAD I, Palakkad
Promised date
20 Sept 2028
no date change on file
19 May 2028
no date change on file
Physical %
55%
not filed
20%
not filed
Booked %
46%
53 of 116
13%
2 of 16
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q2 2026
filed 07 Oct 2026 · -34d ago · Current
Q2 2026
filed 06 Oct 2026 · -33d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.