← Projects
Compare
Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Palakkad · 2024 · K-RERA/PRJ/PKD/214/2024
Palakkad · 2024 · K-RERA/PRJ/PKD/025/2024
Same cohort: Palakkad · 2024.
Project
Evening Paradise
VANIYAKULAM II, Palakkad
Hanco Krishna Leela Residency
PALAKKAD I, Palakkad
Promised date
30 Apr 2028
no date change on file
19 May 2028
no date change on file
Physical %
—
not filed
20%
not filed
Booked %
34%
23 of 68
13%
2 of 16
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
never filed
no quarterly update on file
Q2 2026
filed 06 Oct 2026 · -33d ago · Current
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.