Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Palakkad · 2024 · K-RERA/PRJ/PKD/113/2024

Palakkad · 2024 · K-RERA/PRJ/PKD/130/2024

Same cohort: Palakkad · 2024.

As filed
Project
Bright Villaggio
OTTAPALAM II, Palakkad
Neamath Sterling
OTTAPALAM I, Palakkad
Promised date
31 Dec 2024
no date change on file
30 Nov 2029
no date change on file
Physical %
100%
not filed
45%
not filed
Booked %
0%
0 of 109
71%
12 of 17
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
Q2 2026
filed 07 Oct 2026 · -34d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.