Skip to main content
Enthayi?
K-RERA
← Projects

Compare

Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Palakkad · 2024 · K-RERA/PRJ/PKD/113/2024

Palakkad · 2024 · K-RERA/PRJ/PKD/071/2024

Same cohort: Palakkad · 2024.

As filed
PGM RiveraOn Track
Project
Bright Villaggio
OTTAPALAM II, Palakkad
PGM Rivera
MANNARKKAD 1, Palakkad
Promised date
31 Dec 2024
no date change on file
09 Jun 2027
no date change on file
Physical %
100%
not filed
90%
not filed
Booked %
0%
0 of 109
28%
12 of 43
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
Q2 2026
filed 05 Oct 2026 · -32d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.