Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Palakkad · 2024 · K-RERA/PRJ/PKD/113/2024
Palakkad · 2024 · K-RERA/PRJ/PKD/025/2024
Same cohort: Palakkad · 2024.
Project
Bright Villaggio
OTTAPALAM II, Palakkad
Hanco Krishna Leela Residency
PALAKKAD I, Palakkad
Promised date
31 Dec 2024
no date change on file
19 May 2028
no date change on file
Physical %
100%
not filed
20%
not filed
Booked %
0%
0 of 109
13%
2 of 16
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
Q2 2026
filed 06 Oct 2026 · -33d ago · Current