Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Kottayam · 2024 · K-RERA/PRJ/KTM/101/2024

Kottayam · 2024 · K-RERA/PRJ/KTM/190/2024

Same cohort: Kottayam · 2024.

As filed
ASSET ALPZExtended
GardensOverdue
Project
ASSET ALPZ
PUTHUPPALLY KOTTAYAM, Kottayam
Gardens
VALLICHIRA, Kottayam
Promised date
15 Aug 2027
no date change on file
16 Feb 2026
7 months past promised date
Physical %
28%
not filed
95%
not filed
Booked %
13%
2 of 15
10%
1 of 10
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q2 2026
filed 06 Oct 2026 · -33d ago · Current
Q4 2025
filed 06 Apr 2026 · 150d ago · Stale

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.