Skip to main content
Enthayi?
K-RERA
← Projects

Compare

Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Malappuram · 2024 · K-RERA/PRJ/MPM/262/2024

Malappuram · 2024 · K-RERA/PRJ/MPM/191/2024

Same cohort: Malappuram · 2024.

As filed
Project
MALABAR HILLS
PERINTALMANNA, Malappuram
MABCO OPULENCE
PERINTALMANNA, Malappuram
Promised date
28 Mar 2027
no date change on file
31 Dec 2027
no date change on file
Physical %
96%
not filed
40%
not filed
Booked %
72%
54 of 75
87%
13 of 15
Complaints
9
no final order on file
none on file
from the public complaints list
Last QPR
Q2 2026
filed 03 Oct 2026 · -30d ago · Current
Q2 2026
filed 06 Oct 2026 · -33d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.